Hello!
We work with BPCS V 4.05 CD. Actually we manage 2 companies and many
Work Centers for each company. Some of our Work Centers are going to be
under construction in December, so in the Shop Calendar we have December
as S (Shut Down) for no production.
 
 The problem is that MRP500 and MRP600 are taking the General Calendar
for all products and it programs production for these centers while they
are not working.
 
Anyone have any idea how to solve this?
 
Thanks
Maria del Carmen

As an Amazon Associate we earn from qualifying purchases.

This thread ...

Follow-Ups:

Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2025 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.