• Subject: RE: Upgrade Considerations: Software vs Hardware
  • From: "Shurge, Stephen (MTL)" <sshurge@xxxxxxxxxxxx>
  • Date: Thu, 31 Aug 2000 10:51:00 -0400
  • Cc: "Gershen, Al" <aldg5@xxxxxxxxx>

Title: RE: Upgrade Considerations: Software vs Hardware

HI Al:

I would like to offer this experience.

A previous employer went through what you are going through and decided to changed ERP software and hardware.

Here is an some of the results of their decision:

- IT budget has grown from 3 million to 10 million
- The migration costs estimated at 4.1 million cost 7.9 million
- The upgrade and migration costs of Mapics and hardware for 5 years projected growth was estimated at 2.2 million
- Staff turnover was almost total thus loss of staff and experience was very large
- At cuttover NO invoicing was done for a month (cash flow horror)
- The response time promised of 1 second turned out to be 9 seconds when they went live
- Modifications to new ERP at very costly
- The new ERP was a very fast growing software that has now experienced hard times and is near Chapter 11


The best comment I could offer is: "The grass is not always green on the other side of the fence" and "You never know
how well off you were until you try something else (but what a price to pay because there is usually no way back)

Good Luck





This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2026 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.