Hi all,
We're using a 3rd party to migrate our Power7 to a Power8.
We received an email this morning that says:
Until the end of March can you please defer all PTF’s and cumes until
after we migrate to Power8.
I normally check for HIPER and other PTFs every Friday. It seems strange
to me to have a freeze period for the next 7 weeks. If it was me, I'd want
to make sure I had the latest fixes.
Two questions:
1. Is there an IBM recommended practice on this?
2. What strategy are you using?
Yours truly,
Glenn Gundermann
Email: glenn.gundermann@xxxxxxxxx
Work: (416) 675-9200 ext. 89224
Cell: (416) 317-3144
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2025 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact
[javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.