Jon,
Well, that would depend on the route he decides to take for his upgrade.
If he's going to upgrade his old box to 7.1 before transferring --
then I would recommend going to 7.1 first on the old box, then move that
to the new box, then upgrade the new box from 7.1 to 7.3. Depending on
the window of downtime allowed, this might not be feasible to do all at
once, and may have to be split across multiple "windows."
Going to 7.3 on his old box will almost certainly not work, as the old
box probably doesn't support a release that new. And IBM doesn't
support a direct data migration from 5.4 to 7.3, anyway. (Another
problem with waiting this long!)
If he decides to just save his user libraries and restore them on the
new box, then then he might as well skip 7.1 and 7.2 completely and just
restore straight onto a 7.3 box. This is one of the tradeoffs of going
through all the pain of reconfiguring all your settings -- you don't
need a migration path that IBM blesses :-)
But you're absolutely right... if you're going to go through the work
of upgrading, you might as well go to the latest and greatest. If you
can pick between 7.3 and 7.1 there's absolutely no advantage or value to
picking 7.1. 7.3 has everything that 7.1 had, plus more, and no down
sides that I've seen.
-SK
On 5/26/2016 7:55 PM, Jon Paris wrote:
Would add to Scott’s comment the suggestion that having moved to V7.1
you immediately go to V7.3 0 there is really little point in gong
from one outdated release to another.